Project Updates
126th, 131st, 135th and 146th interchanges have been completed.
141st Street and State Road 37 Update
The final interchange of the State Road 37 Improvement Project will officially begin construction at 141st St. and State Road 37 this summer. The pre-construction meeting for the project team will take place at the end of May with the schedule to soon follow. One important note: To ease the construction burden in the area, the work will not begin until Hamilton County’s 146th St. closure at Allisonville re-opens.
What to Expect this Summer
The interim traffic configuration that has been in place will be removed, with construction beginning on the west side of 141st. During this time, all traffic will be moved to the east side, with a north and southbound lane open at all times on SR37. All construction updates will be posted to DriveFishers on X (Twitter) and 37Thrives on Facebook. Please visit 37thrives.com to sign-up for email updates.
January 2023:
-Pre-construction phase begins.
-141st Street transitions to a temporary right-in-right-out (RIRO) configuration.
-Prep work is initiated, including utilities relocation.
April 2024:
-Project is put out for bid.
-Gradex Inc is awarded the contract for $37.6 million.
June/July 2024:
-Anticipated start date for construction.
-Project commencement delayed until after the interchange at 146th and Allisonville reopens to reduce traffic impact.
This timeline outlines the key milestones and events in the construction updates for 141st Street and SR 37. Updates that include project phases and timelines of construction will be shared in the coming weeks.