Menus skipped, continue to page content.

See the Road Status Map

Welcome to Drive Fishers, your go-to source for the latest road construction updates, traffic impacts, infrastructure projects, and transportation improvements happening throughout our city. Our goal is to keep residents informed so you can plan ahead, travel safely, and stay connected to the projects that help Fishers remain a vibrant, growing community. Check back regularly for updates, project details, and real-time information on road closures and construction activity.

Weekly Construction Update

Road Notice Updates for the Week of July 27

All work is weather-dependent and subject to change. This update highlights major closures and traffic impacts, but may not include every Department of Public Works project.

🚩Road Closures and Traffic Impacts – At a Glance🚩


  • 96th Street and Cyntheanne Road – Full ClosureFollow detour route
  • 136th Street Widening – Southeastern Parkway to Prairie Baptist Road – Follow detour route
  • 116th Street and Allisonville Road Intersection Improvements Project –Down to one lane in all directions – Traffic Phase 2 Now in place
  • Southeastern Parkway & Olio Road Roundabout Improvements – Periodic lane restrictions
  • 126th Street – Single-lane restrictions (beginning July 13)
  • Fishers Crossing Blvd – closed west of Allisonville beginning July 27 (For three weeks)

🚧Major Closures and Detours 🚩


🚧96th Street & Cyntheanne Road – CLOSURE IN PLACE

Construction of the new roundabout at 96th Street and Cyntheanne Road has begun and a full closure is in place at this intersection.

What Drivers Should Expect

  • Full intersection closure to traffic
  • Signed detour routes around the intersection
  • Local access maintained for nearby properties
  • Additional travel time in the area

View the detour route here.

🚧 136th Street Widening – Southeastern Parkway and Prairie Baptist Road

Construction is underway on the Southeastern Parkway and Olio Road roundabout to improve safety and traffic flow at one of the region’s busiest intersections. 

Currently, the roundabout remains open with no lane restrictions through early August. Olio Road is reduced to one lane southbound.  

Beginning in early August, drivers should expect lane restrictions, including Olio Road reduced to one lane in each direction and closure of the “5th leg” of the roundabout. 

Detour and traffic maps for Phase 2 will be shared before that phase begins in October. Details: fishersin.gov/olio

Road Improvements at 116th St & Allisonville Rd – Traffic Shift Update and Road Closure

Fishers Crossing Access Closure

Beginning MONDAY, July 27, the west leg of Fishers Crossing Blvd at Allisonville Road will close for approximately three weeks, weather permitting.

During the closure, motorists will not be able to enter or exit the Fishers Crossing Shopping Center area at this connection to Allisonville Road. Drivers should use an alternate entrance and follow posted signage.

This closure is necessary to support ongoing construction for the 116th Street and Allisonville Road Improvement Project.

As of Thursday, July 16, crews have implemented the next major traffic shift as construction continues at the 116th Street and Allisonville Road intersection.

What to Expect

  • The outside lanes at the intersection will be closed.
  • Traffic will be shifted to the inside through lanes and designated turn lanes.
  • All businesses will remain open and accessible throughout construction.
  • This traffic pattern is expected to remain in place through early October, weather permitting.

Motorists are encouraged to slow down, use caution, follow posted signage, and allow extra travel time when traveling through the area.

Stay Connected

For the latest construction updates:

  • Drive Fishers Road Construction Updates: FishersIN.gov/RoadConstruction
  • Follow @DriveFishers on X
  • Subscribe to the Drive Fishers Newsletter: FishersIN.gov/Subscribe
  • Subscribe to the Allisonville Corridor Newsletter: FishersIN.gov/Allisonville

Questions? Contact the Engineering Department at drivefishers@fishersin.gov.

🚦 Utility Work 🚨


Cumberland Road Utility Work – Duke Project

Lane restrictions continue between 106th Street and 116th Street from 9 a.m. to 3 p.m.

ATT Utility Work

ATT will be installing fiber throughout the following neighborhods: Beaver Ridge, Pine Bluff Overlook, Bradford Ridge, Walnut Creek, Delaware Pointe, Summerfield, Delaware Crossing. Work will be begin in the next week and will be conducted in utility easements behind the sidewalk.

🚧 Project Updates


USA Parkway Widening Project (North of 106th Street)

Beginning Monday, August 3, motorists should expect lane restrictions on USA Parkway north of 106th Street as construction begins on the USA Parkway Widening Project. Lane restrictions are expected to remain in place through October, weather permitting.

Work will include roadway widening, new curb improvements, trail construction, and pavement resurfacing. Traffic will be maintained throughout construction, and access to businesses and driveways will remain open. Motorists should expect periodic traffic shifts, reduced speeds, and occasional delays while crews work.

The project is anticipated to reach substantial completion in mid-October, with final restoration and punch list work continuing into November.

Please slow down, watch for construction crews, and allow extra travel time when traveling through the area. As always, schedules are weather dependent and subject to change.

Resurfacing Projects

Road Resurfacing and Trail Work Update

Crews are expected to continue resurfacing, trail, pavement marking, and restoration work from late July through early August. All work is weather permitting and schedules may change based on field conditions.

Resurfacing Package 26-1

Work includes milling and base repair in the Weaver neighborhoods, milling in Rosewood, and upcoming milling on 96th Street from Carroll Road to Olio Road.

Paving is expected to begin on Harrison Parkway on July 31, with additional paving in the Weaver neighborhoods planned for August 1.

Resurfacing Package 26-2

During late July, crews are scheduled to complete roadway milling along 131st Street and Howe Road.

Asphalt paving is expected to follow during the final week of July, beginning on 131st Street and continuing onto Howe Road through approximately the end of the week.

Mainline pavement striping will follow once paving operations are complete. A specific striping schedule has not yet been determined.

What Drivers Should Expect

Motorists may encounter temporary lane restrictions, flaggers, construction equipment, and short delays in active work areas. Work along the main roadways is generally expected to take place between approximately 8:30 a.m. and 3:30 p.m.

Southeastern Parkway & Olio Road Roundabout Improvements

Construction is underway on the Southeastern Parkway and Olio Road roundabout to improve safety and traffic flow at one of the region’s busiest intersections. 

Currently, the roundabout remains open with no lane restrictions through early August. Olio Road is reduced to one lane southbound.  

Beginning in early August, drivers should expect lane restrictions, including Olio Road reduced to one lane in each direction and closure of the “5th leg” of the roundabout. 

Detour and traffic maps for Phase 2 will be shared before that phase begins in October. Details: fishersin.gov/olio

State Road 37 Improvement Project


State Road 37 and 141st Street

The State Road 37 Improvement Project at 141st Street is now substantially complete, and the City celebrated the official ribbon cutting for the new interchange on May 26.

Motorists should expect periodic lane restrictions and intermittent work activity throughout the corridor as contractors complete final punch-list items and remaining project details, including landscaping and minor finishing work.

Drivers are encouraged to continue using caution in the area while crews complete these final activities. Signage will be removed once all operations are complete.

Learn more on the Drive Fishers page and follow @DriveFishers on X for updates. Questions? Email Drive Fishers.

🚗 Regional Construction🛣️


The following projects are managed by partner agencies and may impact Fishers-area drivers.

EAST CARMEL PEDESTRIAN SAFETY IMPROVEMENTS:

April 1 – early August
As of April 1, extensive work has begun on the east side of Carmel to install raised pedestrian crosswalks within several roundabouts along Hazel Dell Parkway and Gray Road. 

Phase 4 (46-day closure, summer break) NOW OPEN
116th Street and Hazel Dell Parkway

Phase 5 (30-day closure) TBD
Main Street and Gray Road

All raised pedestrian crosswalk installations are set for completion in September, reinforcing Carmel’s ongoing commitment to student and neighborhood safety.

For more details visit the City of Carmels website.

Clear Path Improvement Project 

Upcoming Short-Term Closures

Friday, July 24 (9 p.m. to 6 a.m.)

Westbound I-465 reduced to one lane between I-69 and Allisonville Rd while crews install overhead signage.

Saturday, July 25 (9 p.m. to 6 a.m.)

Northbound I-465 to northbound I-69 ramp reduced to one lane for temporary barrier wall and pavement markings. 

Long-Term Closures

82nd Street Ramps

82nd Street ramps – current configuration

New lanes of I-465,  Allisonville Road ramp NOW OPEN

Click HERE to learn more. 

For more information Visit the Clearpath465 website.