
See the Road Status Map
Welcome to Drive Fishers, your go-to source for the latest road construction updates, traffic impacts, infrastructure projects, and transportation improvements happening throughout our city. Our goal is to keep residents informed so you can plan ahead, travel safely, and stay connected to the projects that help Fishers remain a vibrant, growing community. Check back regularly for updates, project details, and real-time information on road closures and construction activity.
Weekly Construction Update
Road Notice Updates for the Week of August 10
All work is weather-dependent and subject to change. This update highlights major closures and traffic impacts, but may not include every Department of Public Works project.
🚩Road Closures and Traffic Impacts – At a Glance🚩
- USA Parkway Widening – Lane restrictions through October
- 96th Street & Cyntheanne Road – Periodic lane restrictions
- 136th Street Widening – Detour in place between Southeastern Parkway & Prairie Baptist Road
- 116th Street & Allisonville Road – One lane in each direction (Traffic Phase 2)
- Southeastern Parkway & Olio Road Roundabout – Periodic lane restrictions
- Fishers Crossing Blvd –closed through the end of the month
🚧Major Closures and Detours 🚩
🚧96th Street & Cyntheanne Road – Ongoing Lane Restrictions
A roundabout at 96th Street and Cyntheanne Road has been constructed to replace the former intersection. This roundabout has now opened to traffic with lane restrictions in place between 9am to 3pm as the contractor finishes up final details.
🚧 136th Street Widening – Southeastern Parkway and Prairie Baptist Road
Construction is underway on the Southeastern Parkway and Olio Road roundabout to improve safety and traffic flow at one of the region’s busiest intersections.
Currently, the roundabout remains open with no lane restrictions through early August. Olio Road is reduced to one lane southbound.
Beginning in early August, drivers should expect lane restrictions, including Olio Road reduced to one lane in each direction and closure of the “5th leg” of the roundabout.
Detour and traffic maps for Phase 2 will be shared before that phase begins in October. Details: fishersin.gov/olio
Road Improvements at 116th St & Allisonville Rd – Traffic Shift Update and Road Closure
Fishers Crossing Access Closure
As of August 5, the west leg of Fishers Crossing Blvd at Allisonville Road has been closed and will remain closed until the end of August, weather permitting.
During the closure, motorists will not be able to enter or exit the Fishers Crossing Shopping Center area at this connection to Allisonville Road. Drivers should use an alternate entrance and follow posted signage.
This closure is necessary to support ongoing construction for the 116th Street and Allisonville Road Improvement Project.
As of Thursday, July 16, crews have implemented the next major traffic shift as construction continues at the 116th Street and Allisonville Road intersection.
What to Expect
- The outside lanes at the intersection will be closed.
- Traffic will be shifted to the inside through lanes and designated turn lanes.
- All businesses will remain open and accessible throughout construction.
- This traffic pattern is expected to remain in place through early October, weather permitting.
Motorists are encouraged to slow down, use caution, follow posted signage, and allow extra travel time when traveling through the area.
Stay Connected
For the latest construction updates:
- Drive Fishers Road Construction Updates: FishersIN.gov/RoadConstruction
- Follow @DriveFishers on X
- Subscribe to the Drive Fishers Newsletter: FishersIN.gov/Subscribe
- Subscribe to the Allisonville Corridor Newsletter: FishersIN.gov/Allisonville
Questions? Contact the Engineering Department at drivefishers@fishersin.gov.
🚦 Utility Work 🚨
Cumberland Road Utility Work – Duke Project
Lane restrictions continue between 106th Street and 116th Street from 9 a.m. to 3 p.m.
ATT Utility Work
ATT will be installing fiber throughout the following neighborhods: Beaver Ridge, Pine Bluff Overlook, Bradford Ridge, Walnut Creek, Delaware Pointe, Summerfield, Delaware Crossing. Work will be begin in the next week and will be conducted in utility easements behind the sidewalk.
🛜Upcoming Brightspeed Fiber Installation
Brightspeed is expected to begin fiber installation work next week in the following neighborhoods:
- The Boulders
- Reserve at Steeplechase
- Sanctuary at Steeplechase
- Oakhurst
Residents may notice door hangers being distributed and utility locate flags appearing in advance of construction. These are part of the preparation process before work begins. For more information on Fiber installation and what you can expect, please visit https://fishersin.gov/services-resources/resident-resources/homeowners-associations/
🚧 Project Updates
USA Parkway Widening Project (North of 106th Street)
Motorists should expect lane restrictions on USA Parkway north of 106th Street as construction begins on the USA Parkway Widening Project. Lane restrictions are expected to remain in place through October, weather permitting.
Work will include roadway widening, new curb improvements, trail construction, and pavement resurfacing. Traffic will be maintained throughout construction, and access to businesses and driveways will remain open. Motorists should expect periodic traffic shifts, reduced speeds, and occasional delays while crews work.
The project is anticipated to reach substantial completion in mid-October, with final restoration and punch list work continuing into November.
Please slow down, watch for construction crews, and allow extra travel time when traveling through the area. As always, schedules are weather dependent and subject to change.
Resurfacing Project
During the week of August 17:
The contractor will be completing concrete operations in Fawnsbrook neighborhood ahead of milling and paving as well as begnning work on Westmoreland Dr. in the Somerset neighborhood. More details will be provided in the future regarding upcoming operations in the Weaver Neighborhoods.
Upcoming work includes milling and base repair on 96th Street from Carroll Road to Olio Road. All work is weather dependant.
Homeowners will be notified via door hangers prior to any curb reconstruction near their home. After ADA ramp and curb reconstruction is completed, those areas will be restored with topsoil and seed. It is the responsibility of the homeowner to water the seed for the seed to germinate. Following concrete operations contractors will begin performing asphalt road resurfacing and additional notices will be provided. Residents will also be notified via street signage for street parking restrictions.
For additional project information, view the Capital Project Dashboard here.
Southeastern Parkway & Olio Road Roundabout Improvements
Construction is underway on the Southeastern Parkway and Olio Road roundabout to improve safety and traffic flow at one of the region’s busiest intersections.
Currently, the roundabout remains open with no lane restrictions through early August. Olio Road is reduced to one lane southbound.
Beginning in early August, drivers should expect lane restrictions, including Olio Road reduced to one lane in each direction and closure of the “5th leg” of the roundabout.
Detour and traffic maps for Phase 2 will be shared before that phase begins in October. Details: fishersin.gov/olio
State Road 37 Improvement Project
State Road 37 and 141st Street
The State Road 37 Improvement Project at 141st Street is now substantially complete, and the City celebrated the official ribbon cutting for the new interchange on May 26.
Motorists should expect periodic lane restrictions and intermittent work activity throughout the corridor as contractors complete final punch-list items and remaining project details, including landscaping and minor finishing work.
Drivers are encouraged to continue using caution in the area while crews complete these final activities. Signage will be removed once all operations are complete.
Learn more on the Drive Fishers page and follow @DriveFishers on X for updates. Questions? Email Drive Fishers.
🚗 Regional Construction🛣️
The following projects are managed by partner agencies and may impact Fishers-area drivers.
Hamilton County Highway Department
LANE RESTRICTIONS – CUMBERLAND ROAD – BRIDGE 164 OVER MUD CREEK
Please be advised, on Thursday, August 6, 2026, drivers should expect daily lane restrictions on Cumberland Road, south of 116th Street, for bridge preservation work. The expected completion date for this project is Friday, August 21, 2026. Please use extreme caution while driving through the construction zone. Drivers are encouraged to be vigilant and watch for flaggers in the area.
Clear Path Improvement Project
Upcoming Short-Term Closures
Drivers can expect the following closures:
Lane and ramp closures are scheduled this weekend on I-465 and I-69 in northeast Indianapolis in preparation of opening new ramps and travel lanes.
Westbound I-465 is scheduled to be reduced to one lane between I-69 and the White River from 9 p.m. Friday, Aug. 14, through 6 p.m. Sunday, Aug. 16. Crews will install pavement markings and signage. Work will begin closest to the median Friday night and shift to the outer lanes Saturday evening.
The following ramps are scheduled to close from 9 p.m. Saturday, Aug. 15 and reopen by 6 p.m. Sunday, Aug. 16:
- Ramp from southbound I-69 to westbound I-465
- Signed Detour:Southbound I-69 to southbound I-465 and turn around at Pendleton Pike (U.S. 36).
- Ramp from westbound I-465 to Allisonville Road
Ramp from Allisonville Road to westbound I-465
Monday, Aug. 10 – Friday, August 14 (nightly 9 p.m. to 6 a.m.)
- Northbound I-465 single lane closure from Fall Creek to the I-69 interchange.
Thursday, August 13 (9:00 p.m. – 6:00 a.m.)
- Ramp from northbound I-465 / northbound I-69 to 82nd closed
- Ramp from southbound I-69 to westbound I-465 / southbound Binford Blvd. single lane closure
- Ramp from northbound I-465 to northbound I-69 reduced to one lane
- Southbound I-69 single lane closure from 86th to the I-465 interchange
Long-Term Closures
- Ramp from 56th Street to northbound I-465 closed
- Ramp from northbound Binford Boulevard to westbound I-465 closed
82nd Street Ramps
82nd Street ramps – current configuration
New lanes of I-465, Allisonville Road ramp NOW OPEN
Click HERE to learn more.
For more information Visit the Clearpath465 website.
Get Drive Fishers Updates in Your Inbox
Subscribe to receive weekly Drive Fishers construction updates in your inbox every Friday.

