Menus skipped, continue to page content.

See the Road Status Map

Welcome to Drive Fishers, your go-to source for the latest road construction updates, traffic impacts, infrastructure projects, and transportation improvements happening throughout our city. Our goal is to keep residents informed so you can plan ahead, travel safely, and stay connected to the projects that help Fishers remain a vibrant, growing community. Check back regularly for updates, project details, and real-time information on road closures and construction activity.

Weekly Construction Update

Road Notice Updates for the Week of August 31

All work is weather-dependent and subject to change. This update highlights major closures and traffic impacts, but may not include every Department of Public Works project.

🚩Road Closures and Traffic Impacts – At a Glance🚩


  • USA Parkway Widening – Lane restrictions through October
  • 96th Street & Cyntheanne Road – NOW OPEN
  • 136th Street Widening – Detour in place between Southeastern Parkway & Prairie Baptist Road
  • 116th Street & Allisonville Road – One lane in each direction (Traffic Phase 2) – Fishers Crossing Access Closure
  • Southeastern Parkway & Olio Road Roundabout – Periodic lane restrictions
  • Fishers Crossing Blvd –Closed through the end of the month
  • 131st and Brooks School Road – Utility relocation in progress – periodic lane restrictions are possible

🚧Major Closures and Detours 🚩


🚧 136th Street Widening – Southeastern Parkway and Prairie Baptist Road

Construction is underway on the Southeastern Parkway and Olio Road roundabout to improve safety and traffic flow at one of the region’s busiest intersections. 

Currently, the roundabout remains open with no lane restrictions through early August. Olio Road is reduced to one lane southbound.  

Beginning in early August, drivers should expect lane restrictions, including Olio Road reduced to one lane in each direction and closure of the “5th leg” of the roundabout. 

Detour and traffic maps for Phase 2 will be shared before that phase begins in October. Details: fishersin.gov/olio

Road Improvements at 116th St & Allisonville Rd

Fishers Crossing Access Closure

As of August 5, the west leg of Fishers Crossing Blvd at Allisonville Road has been closed for approximately three weeks, weather permitting.

During the closure, motorists will not be able to enter or exit the Fishers Crossing Shopping Center area at this connection to Allisonville Road. Drivers should use an alternate entrance and follow posted signage.

Additionally, sidewalks within the project area are closed.

This closure is necessary to support ongoing construction for the 116th Street and Allisonville Road Improvement Project. Crews are currently reconstructing the west side of Allisonville Road at Fishers Crossing Drive as part of this work.

Current Construction Activity

While construction activity may not always be visible from every part of the project area, the contractor continues to work throughout the project limits in several locations at once. Current work includes:

  • Replacing driveway approaches
  • Painting streetlights
  • Installing temporary traffic signals
  • Reconstructing the roadway on the west side of Allisonville Road at Fishers Crossing Drive

Drivers may see crews and equipment shifting between different areas of the project as this work progresses.

As of Thursday, July 16, crews implemented the next major traffic shift as construction continues at the 116th Street and Allisonville Road intersection.

What to Expect

  • The outside lanes at the intersection will be closed.
  • Traffic will be shifted to the inside through lanes and designated turn lanes.
  • All businesses will remain open and accessible throughout construction.
  • This traffic pattern is expected to remain in place through early October, weather permitting.

Motorists are encouraged to slow down, use caution, follow posted signage, and allow extra travel time when traveling through the area.

Stay Connected

For the latest construction updates:

  • Drive Fishers Road Construction Updates: FishersIN.gov/RoadConstruction
  • Follow @DriveFishers on X
  • Subscribe to the Drive Fishers Newsletter: FishersIN.gov/Subscribe
  • Subscribe to the Allisonville Corridor Newsletter: FishersIN.gov/Allisonville

Questions? Contact the Engineering Department at drivefishers@fishersin.gov.

🚦 Utility Work 🚨


Cumberland Road Utility Work – Duke Project

Lane restrictions continue between 106th Street and 116th Street from 9 a.m. to 3 p.m.

ATT Utility Work

ATT will be installing fiber throughout the following neighborhods: Beaver Ridge, Pine Bluff Overlook, Bradford Ridge, Walnut Creek, Delaware Pointe, Summerfield, Delaware Crossing. Work will be begin in the next week and will be conducted in utility easements behind the sidewalk.

🛜Upcoming Brightspeed Fiber Installation

Brightspeed will be working on fiber installation work next week in the following neighborhoods:

  • The Boulders
  • Reserve at Steeplechase
  • Sanctuary at Steeplechase
  • Oakhurst

Residents may notice door hangers being distributed and utility locate flags appearing in advance of construction. These are part of the preparation process before work begins. For more information on Fiber installation and what you can expect, please visit https://fishersin.gov/services-resources/resident-resources/homeowners-associations/

🚧 Project Updates


🚦 96th Street & Cyntheanne Road is now OPEN!

The intersection is fully operational and open to traffic in all directions.

Drivers may still see crews in the area completing occasional final punch-list items, so please continue to use caution when traveling through the intersection.

Thank you for your patience throughout construction! 🚧

131st and Brooks School Road Roundabout

A new roundabout will be constructed at the intersection of 131st Street and Brooks School Road. Drivers can expect periodic lane restrictions in the current utility relocation phase.

USA Parkway Widening Project (North of 106th Street)

Motorists should expect lane restrictions on USA Parkway north of 106th Street as construction begins on the USA Parkway Widening Project. Lane restrictions are expected to remain in place through October, weather permitting.

Work will include roadway widening, new curb improvements, trail construction, and pavement resurfacing. Traffic will be maintained throughout construction, and access to businesses and driveways will remain open. Motorists should expect periodic traffic shifts, reduced speeds, and occasional delays while crews work.

The project is anticipated to reach substantial completion in mid-October, with final restoration and punch list work continuing into November.

Please slow down, watch for construction crews, and allow extra travel time when traveling through the area. As always, schedules are weather dependent and subject to change.

Resurfacing Project

During the week of August 24:

Resurfacing Project Update

Crews will continue milling, base repair, and paving operations in several neighborhoods over the coming weeks. All work is weather dependent and schedules may change based on field conditions.

Upcoming Work

August 26

  • Milling continues in Fawnsbrook
  • Base repair begins in Weaver Woods and Weaver Woods North

August 27

  • Base repair continues in Weaver Woods and Weaver Woods North
  • Milling begins on Westmoreland Drive in the Somerset neighborhood

August 28

  • Base repair in Fawnsbrook

August 29

  • Base repair on Westmoreland Drive

Paving Schedule

August 30

  • Paving begins in Weaver Woods and Weaver Woods North

September 1

  • Paving continues in Weaver Woods and Weaver Woods North
  • Paving begins in Fawnsbrook

September 2

  • Paving continues in Fawnsbrook
  • Paving begins on Westmoreland Drive

September 3

  • Crews anticipate finishing paving on Westmoreland Drive

What Residents Should Know

Residents should expect construction equipment, temporary parking restrictions, and short delays in active work areas. Street signage will be posted in advance of parking restrictions, and additional notifications will be provided as work progresses.

All work is weather dependent and the schedule may shift based on field conditions.

For additional project information, view the Capital Project Dashboard here.

Southeastern Parkway & Olio Road Roundabout Improvements

Construction is underway on the Southeastern Parkway and Olio Road roundabout to improve safety and traffic flow at one of the region’s busiest intersections. 

Currently, the roundabout remains open with no lane restrictions through early August. Olio Road is reduced to one lane southbound.  

Beginning in early August, drivers should expect lane restrictions, including Olio Road reduced to one lane in each direction and closure of the “5th leg” of the roundabout. 

Detour and traffic maps for Phase 2 will be shared before that phase begins in October. Details: fishersin.gov/olio

Geist Waterfront Triathlon – Traffic Impacts

The Geist Waterfront Triathlon will take place on Sunday, August 30, beginning at 7:30 a.m. at Geist Waterfront Park, 10811 Olio Road.

Drivers traveling in the Geist area that morning should expect temporary traffic impacts, police-assisted intersections, cyclists on area roadways, and possible delays along the bike course. The bike course will remain generally open to traffic, but police will stop traffic at necessary intersections to allow cyclists the right of way. A short section of Olio Road near the park will have one lane dedicated to cyclists as participants begin and finish each lap.

The run portion will also use paved trails and neighborhood streets near Geist Reservoir, so motorists should remain alert for participants and event activity throughout the area.

Drivers are encouraged to allow extra travel time, use caution, follow directions from law enforcement and event staff, and watch for cyclists and runners during the event.

🚗 Regional Construction🛣️


The following projects are managed by partner agencies and may impact Fishers-area drivers.

Clear Path Improvement Project 

Upcoming Short-Term Closures

Lane and ramp closures are planned on northbound I-465 in northeast Indianapolis this weekend as crews prepare to shift traffic into its final configuration between Fall Creek and I-69. The added capacity is expected allow the ramp from 56th Street to northbound I-465 to reopen.

Northbound I-465 is scheduled to be reduced to one lane between Fall Creek and I-69 from 9 p.m. Friday, Aug. 28 through 10 a.m. Sunday, Aug. 30. Crews will install pavement markings and signage to open the roadway.

Work will begin closest to the median Friday night and shift to the outer lanes Saturday evening. As work moves to the outside, the ramp from northbound I-465 to northbound I-69 will close from 9 p.m. Saturday, Aug. 29 to 10 a.m. Sunday, Aug. 30. Drivers can use the signed detour to westbound I-465 and turn around at U.S. 421.

Delays are expected, and drivers should plan ahead and seek alternate routes when possible. 

The ramp from 56th Street to northbound I-465 is expected to open next week. Additional lane and ramp closures are planned Monday night to prepare.

Drivers can expect the following restrictions on Monday, Aug. 31, from 9 p.m. to 6 a.m.:

  • Exit ramp from northbound I-465 to 56th Street/Shadeland Avenue (Exit 40) closed
  • Ramps from 56th Street to northbound Shadeland Avenue/I-465 closed
  • Northbound Shadeland Avenue/56th Street collector ramp reduced to one lane, no access to 56th Street

This work is weather dependent. Actual dates and anticipated work may be adjusted if inclement weather or other unforeseen circumstances occur.

Long-Term Closures

  • Ramp from 56th Street to northbound I-465 closed
  • Ramp from northbound Binford Boulevard to westbound I-465 closed

82nd Street Ramps

82nd Street ramps – current configuration

New lanes of I-465,  Allisonville Road ramp NOW OPEN

Click HERE to learn more. 

For more information Visit the Clearpath465 website.